Camino Alto Safe Pathway Project

Project Summary

The proposed Safe Pathway project involves various bicycle and pedestrian improvements along Camino Alto Avenue between Miller and E Blithedale Avenues. Its purpose is to improve connectivity, accessibility, and safety for these modes of transportation. The proposed improvements are identified in the 2008 Safe Routes to School Travel Plan, and include the following components:

  • Possible widening of approximately 120 LF of roadway just north of the Camino Alto/Sycamore Avenue intersection to accommodate future Class II bike lanes on southbound Camino Alto.
  • Installation of bicycle detection cameras or loops at the 3 main traffic signals on Camino Alto between Miller Avenue and E Blithedale Avenue.
  • Installation of accessible curb ramps, realignment of existing crosswalks, and widening of south east corner at the intersection of Camino Alto/Sycamore Avenues.
  • Possible widening of existing multi-use path on east side of Camino Alto between Miller Avenue and Sycamore Avenue.


Project Limits 

Camino Alto Avenue between Miller Avenue and E Blithedale Avenue

Approximate Project Timeline (subject to change)

Design Completion – March 2017 
Construction Advertising Period – April to June 2017 
Construction Project – June to August 2017 

RFP for Engineering Design

The Request for Proposals was issued on June 22, 2016. Proposals are due on July 22, 2016. To submit proposals, visit the City’s bid opening webpage by clicking here, or contact BPXpress Reprographics at 510-559-8299.

Invitation to Bid

To bid on this project, visit the City's electronic plan room at www.blueprintexpress.com/millvalley or contact BPXpress Reprographics at 510-559-8299.

Project Contact 

Cecilia Zamora 
Associate Engineer 
(415) 384-4807 