Project Summary

East Blithedale Avenue is a significant and heavily travelled road, providing access into and out of Mill Valley.  This project has received partial funding through the Transportation Authority of Marin (TAM) Major Roads program is Rehabilitation of East Blithedale Ave from Sunnyside Avenue to Tiburon Boulevard. The project is anticipated to include sanitary sewer, pavement, curb, gutter and sidewalk upgrades.

 

Approximate Project Timeline

August 6, 2018 – Council accepts initial allotment of funding from TAM for completing a feasibility and scoping study.

November 5, 2018 – Council authorizes award of the East Blithedale Avenue Rehabilitation Feasibility and Scoping Study Project to Parisi CSW DESIGN GROUP for an amount not to exceed $74,960. 

March 28, 2019 – Project status meeting held in the Community Center, providing an overview of the corridor's existing conditions core needs and associated cost estimates.

Spring 2020 - Summer 2022  – Design.  Intent is to design entire project up front and to build portions or phases as funds are available.  Phases are currently unknown, but may be geographic, attempting to work on different portions of the corridor, or by work trade, attempting to complete certain tasks such as underground or concrete work first. The project team will make recommendations as design progresses. 

Summer 2021 - Summer 2022 – Construction.  Schedule greatly unknown and dependent upon completion of design, securing required funding and unknown phasing of construction.

 

Project Contact

Ahmed A. Aly, PE
Associate Engineer
(415)384-4755
aaaly@cityofmillvalley.org

 

Attachments

Acceptance of Measure A Funds from TAM - 180806 Staff Report

Award of Feasibility Study - 181105 Staff Report

March 28th Presentation to Community