Miller Avenue Construction Update - Week of August 7 - 11

What happened last week:
Work crews paved the final layer of asphalt concrete on both the fast and slow inbound lanes as well as the outbound slow lane of Miller Avenue from Almonte to Sunnyside. Pedestrian beacons have been installed - please push the buttons to activate.

What is happening this week:
Work crews paved the final layer of asphalt concrete on the outbound lane on Monday. The contractor will now pave the sidestreets, medians, and remaining parking areas. This week's work also includes the raising of sewer manholes and preparing for striping the roadway.

What to expect in the next few weeks:
Striping of the roadway will occur the week of August 21. Crews will continue to raise manholes to proper elevation. Final irrigation work in preparation for landscaping is also scheduled.

Please Note: There will be parking restrictions, lane shifts, and short-term limited driveway/sidestreet access to allow for final paving and striping. Please plan ahead and allow extra time when traveling on Miller Ave.

Click here for the full weekly update.


The City recommends that motorists:

  • Add time to your trip and plan ahead - check out www.mvconnect.org before your trip.
  • Drive slowly through the construction zone.
  • Please be courteous to your neighbors and do not to cut through the residential side streets during the construction period.

City and Construction Management staff are making every effort to mitigate impacts during construction and are working with the Mill Valley Chamber of Commerce to notify local businesses and residents of the planned work. City and Construction Management staff will provide regular updates to the community regarding the project.

Stay Informed

Construction updates will be provided on a weekly basis. Stay informed by signing up for updates here. Follow us on Twitter, Facebook and our project website www.cityofmillvalley.org/millerave.

Questions?

Construction Specific Questions – Please contact Mark Thrailkill with 4LEAF Construction Management at phone (415)328-6972 or email mthrailkill@4leafinc.com.

General Questions – Please contact Linn Walsh, Assistant to the City Manager, City of Mill Valley at lwalsh@cityofmillvalley.org.