Salt Works & Trestle Glen Electrical Improvements Project Update

The Salt Works & Trestle Glen Station electrical improvements is 98% complete.

•Project work involves demolition, temporary systems, installing new electrical Variable Frequency Drive (VFD) pump motor components, equipment, VFD cabinet enclosures, conduits, wiring, start-up and testing at Salt Works and Trestle Glen Pump Stations. 
•The low responsive bid of $258,00 was awarded to D.W. Nicholson on 6/21/2019.  
• Notice to Proceed (NTP) was issued on 7/11/2019.  

 The Factory Acceptance Testing (FAT) was completed on 12/02/2019. The new VFD installation for Salt Works and Trestle Glenn PS started on 1/06/2020. The installation and commissioning testing of three 50 HP VFDs at Salt Works and two 50 HP VFDs at Trestle Glenn PS was completed on 2/7/2020.   Minor punch list items expected to be completed by March 2020.